PROJECT: Constuction of 3-unit classroom block and ancillaries at SDA School at Kalandan

Type of Project

Construction

Project Location

Kalandan SDA

Source of Finance

District Development Facility (DDF)

Contractor

Wabelya co. ltd.

Start Date

04/08/2014

End Date

02/12/2014

Contract Sum

99,931.35

0.18% OF DISTRICT BUDGET

Amount Paid

35,975.29

36% OF CONTRACT SUM

Amount Outstanding

63956.06

64% OF CONTRACT SUM

Percentage (%) of work done

Post your comment

Comments

  • Gravatar for Francisca Darfour

    A report from the Project Associate in Tamale on this project suggest that the 90% given by the Metropolitan Assembly is quite correct. This is because the school blocks has been completed as promised. What is left is the construction of the toilet facilities which was delayed because the stakeholders involved could not agree on the piece of land demarcated for the construction of the toilet facility.
    According to an interview with the Metropolitan Coordinating Director, Alhaji Shehu Kadiri, the Assembly is evaluating other options and will soon come up with a solution to the problem.
    It is our hope the Assembly will make haste in constructing the toilet facilities at SDA school in Kaladan to curb the problem of open defecation and absenteeism in students.


    Posted by Francisca Darfour, 09/11/2015 3:45am (3 years ago)